Project Detail
Project Main Menu

Project Overview
Project Name: PM: McCoart EOC Room Outfitting of AV Equipment
Project Type: AV and Telecommunication Equipment
Project Description: Procurement and installation of AV equipment to the new conference rooms at McCoart building. The project include installation of two videoconferencing systems
Project Manager: Said G. Said     send an email
Alternate Manager: Martha A. Clark     
Agency Name: Department of Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $447,000.00

Revised Budget:

$447,000.00
Original Start Date: 2/24/2009

Revised Start Date:

Original End Date: 10/31/2009

Revised End Date:

11/30/2009
Last Updated On: 4/19/2010 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP Funding

$447,000.00 $447,000.00
       
Total Amount: $447,000.00 $447,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Planning and selection of AV and Telecom. equipment. 2/24/2009 3/26/2009 Said Said  
2. Procurement of Telecom. equipment. 2/25/2009 5/15/2009 OIT Staff  
3. Installation of Telecom. wiring and cabeling systems. 4/20/2009 4/29/2009 Contractor  
4. Preparing IFB Documents for procurement of AV equipment 4/6/2009 4/21/2009 Said& Susan Stanley  
5. Award of Contract 6/19/2009 6/19/2009 PW  
6. Procurement of AV equipment 7/1/2009 8/20/2009 Contractor  
7. Installation of AV equipment 7/15/2009 10/31/2009 Contractor  
8. Programming of AV system 8/17/2009 10/18/2009 Contractor  
9. Training and final tests and acception of the system 9/7/2009 9/15/2009 11/30/2009 Consultant/PWC  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue