Project Detail
Project Main Menu

Project Overview
Project Name: DOT: Rollins Ford Road Widening (Vint Hill Rd. to Songsparrow Dr.)
Project Type: Roadway Improvement
Project Description: The Rollins Ford Road Extension is designated to be a four lane divided roadway with a raised median. The project extends from Vint Hill Road in a northeastern direction 4,300 feet to the existing intersection of Songsparrow Drive and Yellow Hammer Drive.
Project Manager: Thomas J. Blaser     send an email
Alternate Manager: Khattab O. Shammout     
Agency Name: Transportation QPR?: Yes
Magisterial District: Brentsville
Original Budget: $12,000,000.00

Revised Budget:

$12,000,000.00
Original Start Date: 9/15/2011

Revised Start Date:

Original End Date: 8/31/2013

Revised End Date:

Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. 2006 Bond Funding

$12,000,000.00 --- 7/1/2011
       
Total Amount: $12,000,000.00 $12,000,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 9/15/2011 6/30/2012    
2. R-O-W & Utility Relocation 6/30/2012 9/1/2012    
3. Construction 9/1/2012 8/31/2013    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue