Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Coles District Fire and Rescue Station # 6
Project Type: Fire and Rescue Station
Project Description: An approximately 21,000 sf facility that will include sleeping quarters, kitchen, dayroom, offices and apparatus bays.
Project Manager: John W. Mitchell     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Facilities Construction Mgt. QPR?: Yes
Magisterial District: Coles
Original Budget: $9,675,000.00

Revised Budget:

$10,566,923.00
Original Start Date: 12/1/2011

Revised Start Date:

1/1/2013
Original End Date: 11/1/2014

Revised End Date:

12/30/2018
Last Updated On: 8/25/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Funds are available through the fire levy, proffers and debt issuance.

$9,675,000.00 $10,566,923.00 7/1/2012
       
Total Amount: $9,675,000.00 $10,566,923.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design Development Documents received for County review, Design is 35% complete 8/8/2013 1/5/2015    
2. Design Standards Manual adopted by the FRA at the February meeting. 8/8/2013 2/17/2015    
3. Respond to DD submission, FCM has responded to the DD submission, dialog on design ongoing. Anticipate having 50% CD submission week of March 23rd. 1/9/2015 2/17/2015    
4. Submit drawings for permit review 8/1/2015 6/30/2016 11/1/2015 12/12/2016    
5. Development Services issued review comments for revised plans. 12/5/2016 1/5/2017    
6. Submit response to comments to Development Services 1/13/2017 1/23/2017    
7. IFB7004067 advertised for open bidding 4/21/2017 4/21/2017    
8. Bids due June 8, 2017 5/26/2017 5/26/2017 6/8/2017    
9. Construction Contract Awarded to Sorensen Gross Company 7/21/2017 7/21/2017    
10. NTP Issued to Sorensen Gross 7/24/2017 7/24/2017    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
8/25/2017A construction contract was awarded to Sorensen Gross Construction company. The project costs were within budget. The contractor has mobilized and clearing of the site will begin the last week of August.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue