Project Name: DPR: Occoquan Greenway– (Project# 16C13020)
Project Type: New Construction
Project Description: Construct Trail from McCoart Building to the Town of Occoquan
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Recreation QPR?: Yes
Magisterial District: Occoquan
Original Budget: $542,806.00

Revised Budget:

$1,098,312.00
Original Start Date: 7/1/2011

Revised Start Date:

Original End Date: 7/1/2018

Revised End Date:

Last Updated On: 8/18/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers

$0.00 $555,506.00 5/10/2016

2. General Fund

$542,806.00 $542,806.00 7/1/2011
       
Total Amount: $542,806.00 $1,098,312.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Task Order Issued 12/9/15; PO approved 12/9/2015 12/16/2015 Gary Rzepecki  
2. Parks staff met with BOCS May on 5/5/15 to review the plans and answers questions. 5/5/2015 5/5/2015 Gary Rzepecki  
3. Lake Ridge Trail Committee & Lake Ridge HOA Board approved plans. 5/1/2015 5/19/2015 Gary Rzepecki  
4. Trail construction for 3 culverts began. 4/18/2016 5/20/2016 Gary Rzepecki  
5. PO issued for Accubid; Est. start date Oct. 2016. 7/5/2016 7/5/2016 Gary Rzepecki  
6. Segments sent to DSB for approval 7/20/2016 10/21/2016  
7. County Attorney review: Segments 3 and 4 plats approved by LRPRA Full Board on 7/19/16 7/19/2016 12/30/2016  
8. Culverts 4 & 5 for Segments 2 are completed and functioning; Boardwalk completed 1/6/17 11/8/2016 12/5/2016 12/2/2016 1/6/2017 Gary Rzepecki  
9. Plats for segments 3 and 4 revised, resubmitted to LRPRA Board- approved on 3/24/17. 3/24/2016 5/9/2017 Matt White  
10. On 4/25/2017 Parks staff, Supervisor Anderson and the Mayor Quist of the town of Occoquan toured the segments 3 to 6 with Parks staff. 4/25/2017 4/25/2017 Matt White  
11. Plats for segments 3 &4 were approved by the BOCS on May 9, 2017. 5/9/2017 5/9/2017 Matt White  
12. Proposal from Rinker Design received 5/5/17; Meeting with Rinker on 5/11/17 to discuss design proposal. 3/30/2017 5/11/2017 Matt White  
13. Lake RidgeTrail Amendment to Deed of Lease and Trail Easement Plats for Segments 3 and 4 signed by BOCS and recorded in Land Records given to Parks on 7/6/17. 5/9/2017 7/6/2017 Matt White  
14. Meeting with A/E Firm to design bridge crossing for segments 3 and 4 on 8/25/17 8/25/2017 8/25/2017 Matt White  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
7/1/2017Parks is awaiting the A/E list to be completed by Purchasing so we can contact an A/E firm to design the bridge crossings.
Each trail gap needs to have an easement platted, surveyed and a signed agreement in place before we can construct.

2. Schedule/Timing Issues     

 

Date

Issue
11/8/2016Delay in Construction; Construction began for culverts 4 & 5 for Segments 2 on 12/5/16 - original start date 11/8/16 •Boardwalk completion delay due to weather.