Project Name: SW: Landfill Liner Design and Construction of Phase II, Cell B
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct the Phase II, Cell B lined landfill cell.
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $4,100,000.00

Revised Budget:

$3,986,087.00
Original Start Date: 9/1/2011

Revised Start Date:

Original End Date: 12/31/2012

Revised End Date:

1/29/2013
Last Updated On: 7/9/2019 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees and Capital Reserve

$4,100,000.00 $3,986,087.00 7/1/2011
       
Total Amount: $4,100,000.00 $3,986,087.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 9/1/2011 3/2/2012    
2. Invitation for Bid 3/5/2012 6/15/2012    
3. Construction 6/18/2012 12/31/2012 1/29/2013    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
5/8/2013The project is now complete and the County has received certificate to operate (CTO) cell B from DEQ on March 5, 2013. The County is currently placing refuse in this cell. This will be the final report.