Project Detail
Project Main Menu

Project Overview
Project Name: SW: Balls Ford Road Compost Facility Improvements
Project Type: Solid Waste CIP Project - Facility Expansion
Project Description: Provide approximately 3 acres of additional paving to expand and improve the area used to grind brush and collect Household Hazardous Waste, and other safety improvements.
Project Manager: Bernard Osilka     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Brentsville
Original Budget: $700,000.00

Revised Budget:

$700,000.00
Original Start Date: 7/1/2010

Revised Start Date:

Original End Date: 11/30/2012

Revised End Date:

12/30/2012
Last Updated On: 5/9/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Construction (Funded from Solid Waste Fees)

$700,000.00 --- 7/1/2011
       
Total Amount: $700,000.00 $700,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Complete Design 10/1/2010 3/1/2012    
2. Construction 7/1/2012 4/16/2012 10/1/2012 12/19/2012    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue