Project Detail
Project Main Menu

Project Overview
Project Name: Jefferson Davis Hwy South
Project Type: Landscaping
Project Description: Landscaping planned for installation in the Potomac District, along Jefferson Davis Hwy from Joplin Rd to Brady's Hill Rd. The project will consist of 115 trees of various species, shrubs, ornamental grasses, and flowers. The total planting area for the project is 3.71 acres.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Michelle M. Morris     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $75,000.00

Revised Budget:

$75,000.00
Original Start Date: 5/8/2012

Revised Start Date:

Original End Date: 6/5/2012

Revised End Date:

Last Updated On: 8/13/2012 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. $75,000.00 was contributed by Transportation Division to Neighborhood Services Division to design and install the landscaping within the ROW.

$75,000.00 --- 8/6/2011
       
Total Amount: $75,000.00 $75,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
5/8/2012Due to the weather, TD has had to push back their time table. This will have an affect on the starting date for landscaping. The installation date is now scheduled for 5/15/2012.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue