Project Name: NSD: Jefferson Davis Hwy South Phase II
Project Type: Landscaping
Project Description: There will be trees and plantings installed within the medians along Jefferson Davis Hwy from Bradys Hill Rd to Joplin Rd.
Project Manager: Ed W. Wheeling     send an email
Alternate Manager: Michelle M. Morris     
Agency Name: Neighborhood Services QPR?: Yes
Magisterial District: Potomac
Original Budget: $75,000.00

Revised Budget:

$75,000.00
Original Start Date: 10/1/2012

Revised Start Date:

Original End Date: 12/1/2012

Revised End Date:

Last Updated On: 1/23/2015 Maps  Pictures  Documents