Project Detail
Project Main Menu

Project Overview
Project Name: ES: COW BRANCH PHASE II CONSTRUCTION
Project Type: STREAM RESTORATION
Project Description: Restore and stabilize approx 1,700 lf of the Cow Branch tributary to Neabsco Creek from Opitz Blvd to Montgomery Avenue. Includes a $250,000 match grant from DCR (WQIF 2010-P06) (for Phases I & II)
Project Manager: Charles B. Williamson     send an email
Alternate Manager: Thomas E. Dombrowski     
Agency Name: ES QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $350,000.00

Revised Budget:

$350,000.00
Original Start Date: 7/1/2010

Revised Start Date:

Original End Date: 6/30/2016

Revised End Date:

Last Updated On: 9/24/2013 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. WQIF 2010-P06 (DCR Grant)

$0.00 $250,000.00 7/1/2010

2. CIP

$350,000.00 $100,000.00 7/1/2010
       
Total Amount: $350,000.00 $350,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Complete 60% engineering design 7/1/2010 6/30/2013 CBW  
2. Obtain regulatory approvals, JPA, etc. 8/1/2010 11/1/2010 TED  
3. Construction of channel improvements including riffles, channel re-alignment, bank protection 6/1/2012 9/1/2012 9/30/2012 12/31/2012  
4. Planting and vegetation, main channel and tributary 1/1/2013 3/31/2013  
5. annual monitoring, 3 years 6/1/2013 6/1/2016 TED  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue