Project Name: FCM: Charlie T. Deane Police Station
Project Type: Public Safety - Police
Project Description: The Central District Police Station will be a new 57,000 square foot facility located on Davis Ford Road between the Prince William County Parkway and Asdee Lane. The facility will provide police services to the mid- County area, primarily the Dale City, Lake Ridge and Davis Ford Road corridor. Personnel from the Patrol Service Bureau, Criminal Investigations Division, Special Operations Bureau and the Office of the Chief will be located in this facility.
Project Manager: David R. Scott     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Public Works - Facilities Construction Management QPR?: Yes
Magisterial District: Occoquan
Original Budget: $45,508,899.00

Revised Budget:

$28,590,732.00
Original Start Date: 7/1/2005

Revised Start Date:

11/8/2012
Original End Date: 9/30/2011

Revised End Date:

2/9/2018
Last Updated On: 10/31/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Debt Financing

$45,508,899.00 $28,590,732.00 7/1/2012
       
Total Amount: $45,508,899.00 $28,590,732.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design Phase 5/30/2014 5/15/2015    
2. Building Permit Phase 5/18/2015 8/12/2015    
3. Bid Advertisement and Award 8/18/2015 11/17/2015    
4. Construction Phase 11/18/2015 8/29/2017 2/9/2018    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date