Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Adult Detention Center Modular Jail Repairs Phase 2
Project Type: Repairs/Equipment replacement
Project Description: The Phase 2 Scope exterior site work and work within the buildings crawl space including: storm drainage, site grading, repairs to the sanitary and domestic water plumbing systems, installation of dehumidification systems, miscellaneous electrical work, masonry repair and tuck pointing, sealant installation, and mold remediation. The Phase 3 Scope includes sub floor repairs, remediation of minor structural deficiencies, high performance coatings, replacement of floor finishes and vinyl wall base, corner guards, wall and ceiling finishes as needed to facilitate other Work, roofing system and associated sheet metal flashing and trim, food service equipment, dumbwaiter, fire alarm system, lighting fixtures, HVAC ducts, HVAC equipment, HVAC controls, painting, repairs and modernization of the security electronics system, repairs to the storm, sanitary and domestic water plumbing systems, and mold remediation.
Project Manager: John W. Mitchell     send an email
Alternate Manager: Ramesh C. Patel     
Agency Name: Public Works / Adult Detention Center QPR?: Yes
Magisterial District: N/A
Original Budget: $5,000,000.00

Revised Budget:

$5,223,202.00
Original Start Date: 10/1/2012

Revised Start Date:

Original End Date: 3/27/2015

Revised End Date:

10/6/2015
Last Updated On: 2/29/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Adult Detention Center

$5,000,000.00 $5,223,202.00 2/1/2013
       
Total Amount: $5,000,000.00 $5,223,202.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Contract Award to Dustin Construction 6/18/2013 6/18/2013    
2. Notice to Proceed Issued 6/25/2013 6/25/2013 7/8/2013    
3. Project completion 7/8/2013 10/1/2014 10/6/2015    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue