Project Name: SW: Landfill Cap Design and Construction of Phase I, Sequence Two
Project Type: Landfill CIP Project
Project Description: The project includes all work necessary to design and construct a final closure cap for Phase I, Sequence 2.
Project Manager: Sadhu S. Sandhu     send an email
Alternate Manager: Thomas J. Smith     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $2,277,941.00

Revised Budget:

$2,318,762.00
Original Start Date: 10/1/2012

Revised Start Date:

Original End Date: 11/29/2013

Revised End Date:

12/21/2013
Last Updated On: 1/29/2014 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees and Capital Reserve

$2,277,941.00 $2,318,762.00 5/28/2013
       
Total Amount: $2,277,941.00 $2,318,762.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 10/1/2012 3/1/2013    
2. Invitation for Bid (Neogotiate Contract) 3/8/2013 4/28/2013    
3. Construction 5/28/2013 11/29/2013 12/21/2013    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue