Project Detail
Project Main Menu

Project Overview
Project Name: ESD: Dewey's Creek Reach 1 Stream Restoration
Project Type: Stream Restoration Design of Deweys Branch located in the Quantico Watershed
Project Description: Implementation of 1,400 linear feet of stream restoration Dewey's Creek downstream from Rte 1.Permit application submitted to USCOE in January 2017. Plans are approved by County Staff.Construction to begin in September.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $645,000.00

Revised Budget:

$1,002,500.00
Original Start Date: 9/14/2011

Revised Start Date:

6/15/2017
Original End Date: 9/30/2014

Revised End Date:

12/1/2017
Last Updated On: 8/22/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. CIP Funding - Deweys Creek Reach I

$322,500.00 $680,000.00 1/1/1900

2. SLAF Grant Funding of Reach 1

$322,500.00 $322,500.00
       
Total Amount: $645,000.00 $1,002,500.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
Number
of Hours
1. Reviewed Permit Ready Plans of Reach I. 9/14/2011 5/15/2015 9/30/2014 4/15/2017 ted 120
2. Obtain permits for Reach 1 10/15/2015 1/20/2017 1/15/2016 7/1/2017 ted 120
3. Construction 4/15/2017 9/15/2017 12/1/2017 2/1/2018 ted


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue