Project Name: ESD: East Longview Stream Stabilization Project
Project Type: Stream Restoration /Marumsco Creek
Project Description: Stabilize 800 linear feet of Marumsco Creek. Includes the stabilization of the stream bed and banks, and protecting the infrastructure within the stream reach. Project Plans have been reviewed and are approved by the County. Permits secured from US Army Corps of Engineer. Construction and planting is completed.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Joseph C. Morris     
Agency Name: Public Works QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $100,000.00

Revised Budget:

$675,001.00
Original Start Date: 11/30/2012

Revised Start Date:

7/1/2016
Original End Date: 4/30/2013

Revised End Date:

12/1/2016
Last Updated On: 5/16/2017 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. SLAF Grant

$0.00 $268,881.00 5/1/2016

2. CIP

$100,000.00 $406,120.00 5/1/2016
       
Total Amount: $100,000.00 $675,001.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
Number
of Hours
1. Reviewed 60% plans, preparing permit application to obtain water quality permits. Project cost estimate has been completed. 11/30/2012 8/15/2015 ted 40
2. Floodplain Study 4/21/2013 5/1/2015 8/15/2015 ted
3. Construction 6/1/2014 7/1/2016 10/1/2014 1/25/2017 ted


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue