Project Name: ESD: Cow Branch Phase 3
Project Type: Stream Restoration Design in Neabsco Creek Watershed
Project Description: The construction of Cow Branch Phase 3 for approximately 1000 linear feet of restoration is 100 % completed. Project extends from Mellot Road to Opitz Blvd. The Planting of the project area will occur in the Fall of 2015 conducted by Virginia Waters and Wetlands.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works/ESD QPR?: Yes
Magisterial District: Neabsco
Original Budget: $560,000.00

Revised Budget:

$654,081.25
Original Start Date: 2/22/2013

Revised Start Date:

1/1/2015
Original End Date: 12/30/2013

Revised End Date:

12/1/2015
Last Updated On: 2/19/2016 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. The Stormwater Local Assistance Fund (SLAF)Grant

$280,000.00 $301,551.00 12/19/2013

2. CIP

$280,000.00 $352,530.25 12/19/2013
       
Total Amount: $560,000.00 $654,081.25



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
Number
of Hours
1. Reviewed plans 2/22/2013 3/31/2013 9/22/2013 ted 40
2. Secured environmental permits 9/15/2013 10/15/2013 ted 120
3. FEMA Floodplain study Approval 10/15/2013 5/15/2014 ted
4. project construction 7/15/2014 11/15/2014 11/1/2015 Angler Env 400
5. Execute Grant Agreement 4/1/2014 9/1/2014 TED
6. Construction Complete 1/1/2015 6/30/2015 Angler/Env
7. Planting of project area is completed 10/1/2015 12/15/2015 Angler Env


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue
1/16/2014SLAF funds $280,000 matching grant funds awarded by VADEQ to support the construction of this project.

4. Impact on Other Projects     

 

Date

Issue