Project Name: ESD: SWM Facility 77 Retrofit
Project Type: Retrofit - BMP
Project Description: Convert dry detention SWM facility to BMP facility by installing BMP riser.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Occoquan
Original Budget: $30,000.00

Revised Budget:

$148,000.00
Original Start Date: 7/1/2013

Revised Start Date:

8/25/2014
Original End Date: 6/30/2014

Revised End Date:

12/31/2015
Last Updated On: 9/28/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bull Run Watershed

$30,000.00 $148,000.00 7/1/2013
       
Total Amount: $30,000.00 $148,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Construction 5/1/2014 8/25/2014 6/13/2014 11/10/2014 CSB  
2. Fencing Stake out and Installation 6/1/2015 8/1/2015 6/30/2015 10/31/2015 CSB  
3. As-built 10/1/2015 10/31/2015 CBS  
4. Record Easement Addendum 3/5/2014 11/1/2015 5/1/2014 12/31/2015 JA  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue