Project Name: ESD: SWM Facility 98 Retrofit
Project Type: Retrofit - BMP
Project Description: Convert dry detention SWM facility into BMP by installing riser structure and increasing water quality volume.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Woodbridge
Original Budget: $30,000.00

Revised Budget:

$52,616.22
Original Start Date: 7/1/2013

Revised Start Date:

Original End Date: 6/30/2014

Revised End Date:

1/30/2015
Last Updated On: 5/29/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Neabsco Creek Watershed

$30,000.00 $52,616.22 7/1/2013
       
Total Amount: $30,000.00 $52,616.22



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 4/1/2014 5/7/2014 RC  
2. Construction 6/1/2014 10/27/2014 6/30/2014 11/20/2014 CS  
3. As-Built 12/15/2014 1/30/2015 RN  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue