Project Overview
Project Name: B&G: Fire Sprinkler System Installation at Landfill Admin & Heavy Equipment Shop
Project Type: Installation
Project Description: The facility at 14811 Dumfries Road, Manassas, VA was constructed without a sprinkler system; it will be retrofitted with a fire suppression system.
Project Manager: Don H. Flory     send an email
Alternate Manager: Robert M. Weiss     
Agency Name: Buildings & Grounds QPR?: Yes
Magisterial District: Coles
Original Budget: $187,500.00

Revised Budget:

$187,500.00
Original Start Date: 2/1/2012

Revised Start Date:

Original End Date: 11/16/2013

Revised End Date:

1/30/2015
Last Updated On: 6/4/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Received Carryover Funds

$62,500.00 --- 7/1/2012

2. Received Carryover Funds

$125,000.00 --- 7/1/2011
       
Total Amount: $187,500.00 $187,500.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Rinker approved for engineering work 2/1/2012 2/1/2012    
2. Virginia Sprinkler Company (VSC) completed wet tap of main water line 6/1/2012 10/30/2013    
3. VSC waiting on FMO to approve interior plans 10/31/2013 10/31/2013    
4. Board approved contract award to The Matthews Group (TMG) 6/4/2013 11/16/2013    
5. Notice to Proceed issued 7/16/2013 11/16/2013    
6. Plans submitted to Fire Marshal's Office (FMO) 9/11/2013 9/30/2013    
7. Contacted FMO to get project moving again 10/22/2013 10/31/2013    
8. Grounds work completed 10/31/2013 10/31/2013    
9. Email from TMG stating project may need to be rescheduled due to FMO delay 1/6/2014 1/6/2014    
10. FMO advised that a waiver is needed for the code required Fire Dept. access door 1/15/2014 1/15/2014    
11. SAI Engineer emailed draft of waiver for access door to FMO for review 1/27/2014 1/27/2014    
12. SAI Engineer requested an update from FMO 2/12/2014 2/12/2014    
13. Revised waiver submitted to Development Srvs. (DDS) 2/27/2014 2/27/2014    
14. Sprinkler plans emailed to FMO 3/12/2014 3/12/2014    
15. Waiver being recommended for approval and returned to DDS 3/27/2014 3/27/2014    
16. Change Order to be processed due to additional cost for delay 4/11/2014 4/11/2014    
17. Waiver received 1/15/2014 5/8/2014    
18. Contractor received approved Purchase for Change Order #1. 7/2/2014 7/2/2014    
19. Final permits received from Fire Marshall 7/2/2014 7/2/2014    
20. Construction began. Contractor has 120 days from receipt of permits to complete 7/21/2014 11/2/2014    
21. GC working on tying main waterline into the sprinkler system. 11/4/2014 1/26/2015    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue