Project Detail
Project Main Menu

Project Overview
Project Name: ESD: Hopewells Landing - 7800 Zeeland Place
Project Type: Drainage Major Maintenance
Project Description: Remove existing rain garden to improve drainage associated with roadway and lot.
Project Manager: Tony Marquez     send an email
Alternate Manager: Juan P. Alfaro     
Agency Name: Public Works - Environmental Services QPR?: Yes
Magisterial District: Gainesville
Original Budget: $30,000.00

Revised Budget:

$38,728.28
Original Start Date: 7/1/2014

Revised Start Date:

7/7/2014
Original End Date: 10/1/2014

Revised End Date:

6/1/2015
Last Updated On: 6/5/2015 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Drainage Major Maintenance

$30,000.00 $38,728.28 8/1/2014
       
Total Amount: $30,000.00 $38,728.28



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 7/15/2014 8/25/2014 AM  
2. Construction 8/25/2014 9/3/2014 10/1/2014 9/12/2014 CS  
3. Plat Recordation 12/1/2014 2/27/2015 6/1/2015 JA  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue