Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Nokesville Fire & Rescue Station #5 Reconstruction
Project Type: New Construction
Project Description: The Nokesville Fire & Rescue Station was built in 1967 and is located at 12826 Marsteller Drive in Nokesville. This project will replace the current station as recommended in the 2010 Fire and Rescue Facilities Assessment. The new station will be constructed at the same location as the current station. The new station will be approximately 21,000 square feet with expanded office space, sleeping quarters and more suitable apparatus areas.
Project Manager: John W. Mitchell     send an email
Alternate Manager: LouAnn D. Purkins     
Agency Name: Public Works Facilities Construction Management QPR?: Yes
Magisterial District: Brentsville
Original Budget: $9,523,000.00

Revised Budget:

$9,523,000.00
Original Start Date: 1/10/2014

Revised Start Date:

Original End Date: 12/31/2017

Revised End Date:

9/10/2019
Last Updated On: 6/19/2020 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Fire Levy and Proffers

$9,523,000.00 --- 5/21/2014
       
Total Amount: $9,523,000.00 $9,523,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design effort re-started. Space and code issues to be addressed. Design is now at 50% complete. 1/10/2014 3/22/2017    
2. Plans being revised to reflect addition of a Community/Training room to the station. Schematic approved. 11/28/2016 1/13/2017 1/5/2017    
3. 50 percent Construction Documents in process. 1/8/2017 3/29/2017    
4. 50% Design Documents completed 4/7/2017 4/7/2017    
5. 50% cost estimate received 4/7/2017 4/7/2017    
6. Plans Submitted for Permit Review 7/31/2017 9/30/2017    
7. Building Permits approved 7/31/2017 9/30/2017 11/16/2017    
8. IFB for Construction Services issued 1/12/2018 2/20/2018    
9. Issue Notice to Proceed 1/10/2014 12/31/2017 8/23/2019    
10. Substantial Completion 8/23/2018 8/23/2019 8/23/2019    
11. Final Completion including demo of existing fire station 1/10/2014 8/23/2018 8/23/2019 9/10/2019    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue