Project Detail
Project Main Menu

Project Overview
Project Name: ESD: SWM Facility #109 - Water Quality Retrofit
Project Type: Retrofit Construction
Project Description: Convert existing dry pond to Extended Detention BMP
Project Manager: Tony Marquez     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: Public Works QPR?: Yes
Magisterial District: Occoquan
Original Budget: $200,000.00

Revised Budget:

$300,000.00
Original Start Date: 7/1/2016

Revised Start Date:

Original End Date: 6/30/2017

Revised End Date:

7/1/2018
Last Updated On: 10/22/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FY17 CIP

$200,000.00 $300,000.00 7/1/2016
       
Total Amount: $200,000.00 $300,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design 7/1/2016 2/28/2017 6/1/2017 Chao  
2. Construction 4/1/2017 3/1/2018 6/30/2017 7/1/2018 CSB  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue