Project Name: ESD: Dewey's Creek Reach 2 Stream Restoration
Project Type: Stream Restoration
Project Description: Design plans for Reach 2 (4,747 linear feet)have been approved and construction is underway. (Dewey's Creek Phase 1 stream restoration has been awarded a 2019 APWA MID ATLANTIC CHAPTER PROJECT OF THE YEAR) (UNDER 5 MILLION). Only 700 feet of stream to restore. Project to be completed in Otcober 2020.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Benjamin A. Eib     
Agency Name: public works QPR?: Yes
Magisterial District: Potomac
Original Budget: $4,200,000.00

Revised Budget:

$5,785,154.00
Original Start Date: 5/15/2016

Revised Start Date:

Original End Date: 12/15/2017

Revised End Date:

1/25/2021
Last Updated On: 1/25/2021 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Watersheds CIP

$2,800,000.00 $4,035,154.00 5/8/2017

2. SLAF Grant No. 17-05

$1,400,000.00 $1,750,000.00 5/8/2017
       
Total Amount: $4,200,000.00 $5,785,154.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Design of project is at 100% 5/15/2016 12/15/2017 3/1/2018 ted  
2. Final review of project plans 11/15/2017 12/15/2017 3/1/2018 ted  
3. Construction cost estimate being prepared 11/15/2017 12/15/2017  
4. construction 3/15/2018 10/15/2019 1/25/2021 ted  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue