Project Name: ESD: Tributaries to Powells Creek/Vista Drive and Lacrosse Court Tributaries
Project Type: Stream Restoration
Project Description: The restoration of two headwater tributaries to Powell’s Creek. The streams are the Lacrosse Court Tributary and the Vista Drive Tributary. Received a SLAF Grant for $325,000 on May 8, 2017.Design will be received on 8/2018.
Project Manager: Thomas E. Dombrowski     send an email
Alternate Manager: Juan P. Alfaro     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $650,000.00

Revised Budget:

$650,000.00
Original Start Date: 2/15/2017

Revised Start Date:

Original End Date: 12/15/2018

Revised End Date:

12/15/2019
Last Updated On: 10/22/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. SLAF GRANT of 325000 and matching funds of 325000.A total of 650000

$650,000.00 --- 5/8/2017
       
Total Amount: $650,000.00 $650,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Conceptual Project Design 2/15/2017 10/15/2017  
2. 100% design and review 10/15/2017 12/15/2017 8/15/2018  
3. Permits 4/15/2018 7/15/2018 1/15/2019 td  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue