Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Groveton Fire & Rescue Station 22 16C15018
Project Type: New Construction
Project Description: Groveton Station (#22) is a Fire & Rescue station that will be located at 7500 Century Park Drive in the west end of the county. The 21,000 square-foot station will house a pumper, rescue unit, collapse unit, and an Advanced Life Support (ALS) ambulance. Career staffing will be provided for a 24- hour pumper unit, 24-hour rescue unit, and a 24-hour medic unit. The building will include sleeping quarters, a kitchen and dayroom, physical fitness room, training room, storage for heavy tactical rescue equipment, and offices. The station will include four apparatus bays, an area for personal protective equipment, and an exterior training tower
Project Manager: Karen L. FitzGibbon     send an email
Alternate Manager: Christopher D. Phillips     
Agency Name: Department of Fire & Rescue QPR?: Yes
Magisterial District: Gainesville
Original Budget: $16,970,713.00

Revised Budget:

$16,970,713.00
Original Start Date: 7/1/2016

Revised Start Date:

12/1/2017
Original End Date: 1/31/2020

Revised End Date:

1/31/2022
Last Updated On: 3/14/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers approved FY20 (CPR20001)

$262,243.00 --- 7/1/2019

2. Proffers approved FY19 (CPR190001)

$353,095.00 --- 7/1/2018

3. Bond F&R Station 22 (CBD17001)

$15,080,375.00 --- 3/1/2017

4. Fire Levy (CFL16001)

$1,275,000.00 --- 7/1/2015
       
Total Amount: $16,970,713.00 $16,970,713.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Land acquisition completed 7/31/2016 7/27/2017    
2. RFP for A&E Design Services issued 8/4/2017 9/8/2017    
3. A&E Services Contract Award 11/4/2017 11/21/2017    
4. Design Kickoff Meeting 12/8/2017 12/31/2018    
5. Permitting/bid 11/15/2018 4/1/2019 7/11/2019    
6. Construction contract award 3/15/2019 6/25/2019 9/3/2019    
7. Construction 6/26/2019 9/15/2020 12/6/2021    
8. Occupancy/open 9/15/2020 9/30/2020 1/2/2021    
9. Post-occupancy/warranty 1/2/2021 1/2/2022    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue