Project Detail
Project Main Menu

Project Overview
Project Name: DPR:Lake Ridge Boat House Project# 17C13006
Project Type:
Project Description: Develop construction documents to get building into compliance and get occupancy permit.
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Occoquan
Original Budget: $427,978.00

Revised Budget:

$427,978.00
Original Start Date: 10/1/2016

Revised Start Date:

Original End Date: 3/30/2018

Revised End Date:

Last Updated On: 6/14/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bldg & Fac Cap Prog - 18 Alloc

$375,000.00 --- 7/1/2017

2. BOCS16Year End Savings

$52,978.00 --- 7/1/2016
       
Total Amount: $427,978.00 $427,978.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Immediate temporary repairs started in Nov. 2016 11/1/2016 11/30/2016 Ron Lilley  
2. Structural design documents completed 4/20/17. 4/20/2017 4/20/2017 Ron Lilley  
3. Main building repair construction documents submitted on 6/16/17; South addition construction documents submitted on 6/23/17. 6/16/2017 6/23/2017 Ron Lilley  
4. A new proposal in the amount of $73,088 (Job Order Contractor) for the footings and columns work is expected by Aug 8th. 8/8/2017 8/8/2017 Ron Lilley  
5. Under-story work (footings and columns) scheduled to get underway Sept 7th, with 60 days for completion. 9/7/2017 12/7/2017 Ron Lilley  
6. South Addition and internal structural work phase is completing second round of plan review. FEMA Flood Level Certification is pending FEMA approval. (submitted 9/21/2017) 9/21/2017 9/21/2017 Ron Lilley  
7. Approx 90% of new column footers poured 9/27. Remaining footers expected by mid-October. 9/27/2017 10/15/2017 Ron Lilley  
8. Internal structural corrections expected by end of October. •South Addition replacement expected by end of November. 10/20/2017 11/20/2017 Ron Lilley  
9. PO issued 10/25/17 for Exterior Perimeter Support Posts and Additional Structure.( $169,835) 10/25/2017 10/25/2017 Ron Lilley  
10. Adjusted completion dates for remaining work, as follows: • remaining (perimeter) footings – Nov 10 • internal structural corrections – end of November • South addition replacement – end of December 11/10/2017 12/30/2017 Ron Lilley  
11. All footings completed Nov 29. •Internal structural corrections started Nov 27. Completion 12/21. •South addition replacement completion January 30th. 11/29/2017 1/30/2018 Ron Lilley  
12. Construction work completed 2/1/18. 2/1/2018 2/1/2018 Ron Lilley  
13. Code Inspection performed 2/2/18. Passed for Structural/Framing, pending final special inspections report from WDP. •Electrical inspection expected 2/5/18. 2/2/2018 2/5/2018 Ron Lilley  
14. As-built Finish Floor Elevation survey completed and sent to FEMA 2/5/18. 2/5/2018 2/5/2018 Ron Lilley  
15. Anticipate Temporary Occ. Permit until FEMA LOMA issued (probably later Feb). 2/1/2018 2/28/2018 Ron Lilley  
16. All Inspections Completed and released for Occupancy. •As-built documentation expected from WDP by March 9. (Rcvd 3/7/18) •Formal Occ. Permit will be issued upon issuance of LOMA by FEMA – expected by end of March. (Approval issued 3/8/18) 3/7/2018 3/7/2018 Gary Rzepecki  
17. Public Dedication ceremony held March 24, 2018. 3/24/2018 3/24/2018 Gary Rzepecki  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue