Project Detail
Project Main Menu

Project Overview
Project Name: DPR:Pool Gelcoats
Project Type:
Project Description: Pool Gelcoats for Veterans Park, Hammill Mill Park, 3 at Splashdown and 1 at Waterworks.
Project Manager: Tracy L. Hannigan     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: N/A
Original Budget: $138,000.00

Revised Budget:

$138,000.00
Original Start Date: 9/1/2017

Revised Start Date:

Original End Date: 3/30/2018

Revised End Date:

4/27/2018
Last Updated On: 10/29/2018 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Building & Facility Capital Program - FY2018 Allocation

$138,000.00 --- 7/1/2017
       
Total Amount: $138,000.00 $138,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Met with the general contractor and JOC on September 6th to develop scope of work 9/6/2017 9/6/2017 Amarjit Riat  
2. Received proposal from the contractor; Meeting with contractor scheduled for November 6. 11/6/2017 11/6/2017 Amarjit Riat  
3. Proposal received from the contractor for gel coats for slides at Waterworks, Veteran’s Park and Ben Lomond Park on November 12, 2017. Proposal amount $137,000, waiting for transfer of funds. 11/12/2017 11/12/2017 Amarjit Riat  
4. PO in the amount of $137,206.76 processed. Work will begin during March 2018. 12/13/2017 3/30/2018 Amarjit Riat  
5. Update: Work will begin on April 10, 2018 and finish on May 10, 2018. • Work Complete, final inspection April 27, 2018. 4/10/2018 4/27/2018 Amarjit Riat  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue