Project Detail
Project Main Menu

Project Overview
Project Name: ESD: SWM Facility #424 - Water Quality Retrofit
Project Type: Stormwater Retrofit
Project Description: Convert the existing dry detention facility to a constructed wetland to improve the pollutant removal efficiency and obtain TMDL credit.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $434,382.00

Revised Budget:

$545,263.58
Original Start Date: 10/1/2018

Revised Start Date:

9/1/2019
Original End Date: 6/30/2019

Revised End Date:

12/31/2019
Last Updated On: 6/5/2020 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Watershed CIP - SLAF Grant

$215,000.00 $238,972.00 7/1/2017

2. Watershed CIP - SWM Fee Transfer

$219,382.00 $306,291.58 7/1/2017
       
Total Amount: $434,382.00 $545,263.58



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Select Contractor 11/1/2018 12/31/2018 5/1/2019 BAE  
2. Construction 2/15/2019 8/1/2019 5/31/2019 11/30/2019 BAE  
3. Asbuilt Survey 5/31/2019 12/31/2019 6/30/2019 12/31/2019 BAE  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue