Project Detail
Project Main Menu

Project Overview
Project Name: DPRT: Doves Landing (Project# 18C13017)
Project Type: New Construction
Project Description: Parking lot, water access, additional entrance, double the linear foot in trails, and an update to the master plan.
Project Manager: Brendon C. Hanafin     send an email
Alternate Manager:     
Agency Name: Parks & Rec QPR?: Yes
Magisterial District: Coles
Original Budget: $2,447,506.48

Revised Budget:

$2,447,506.48
Original Start Date: 7/1/2018

Revised Start Date:

Original End Date: 9/30/2023

Revised End Date:

Last Updated On: 8/3/2021 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Proffers (All Others) Transfers to Capital Projects- FY20

$2,427,654.48 --- 7/1/2019

2. BOCS FY17 Year End Savings

$19,852.00 --- 7/1/2017
       
Total Amount: $2,447,506.48 $2,447,506.48



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. The Master plan will be updated this winter with the feasibility study for the additional trails and boardwalks completed by spring 2022. 10/14/2020 6/1/2022 Brendon Hanafin  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue