Project Name: SW: Landfill Liner Design and Construction of Phase III, Cell A
Project Type: Landfill CIP Project
Project Description: Project 21C15001 was approved by BOCS Res#20-332, FY21-26 Capital Improvement Program on April 28, 2020. The project includes all work necessary to design and construct the Phase III, Cell A lined landfill cell.
Project Manager: Trent A. Magill     send an email
Alternate Manager: Monica Gorman     
Agency Name: Public Works QPR?: Yes
Magisterial District: Coles
Original Budget: $4,680,000.00

Revised Budget:

$4,680,000.00
Original Start Date: 7/1/2020

Revised Start Date:

Original End Date: 10/31/2022

Revised End Date:

11/30/2021
Last Updated On: 2/10/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Solid Waste Fees

$4,680,000.00 --- 7/1/2020
       
Total Amount: $4,680,000.00 $4,680,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design 7/1/2020 9/1/2020    
2. Invitation for Bid 9/1/2020 1/20/2021    
3. Construction 1/20/2021 10/31/2021    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue
6/25/2020The construction of a liner equipped with a leachate collection system is required to meet State and Federal regulations in order for the landfill to continue to operate and accept waste.

2. Schedule/Timing Issues     

 

Date

Issue
8/12/2021The Contractor has finished liner installation work and all other related work. The Contractor is installing litter fence and is working on punch list items. Cell construction is essentially complete and substantial completion is anticipated by or before end of August and final completion of the project is anticipated by mid September 2021. The certification report is being prepared for submission to DEQ in order to obtain certificate-to-Operate Cell IIIA and is expected to be received from DEQ during the month of October 2021.
6/25/2020Design for the construction of liner cell Phase III, Cell A will be started in July 2020 and completed in November 2021.