Project Detail
Project Main Menu

Project Overview
Project Name: ES: 4954/4956 Linsey Court / Watershed: Neabsco Creek
Project Type: Drainage Improvement Project
Project Description: (Dale City, Sec. 9 D, Project Code Number: 5566) Storm water runoff is causing erosion on properties, and flooding a basement through a window. Need to design and construct a drainage system that will alleviate the problem.
Project Manager: Khalid Quraishi     send an email
Alternate Manager: Mukesh Patel     
Agency Name: Department of Public Works - Environmental Services QPR?: Yes
Magisterial District: Coles
Original Budget: $15,000.00

Revised Budget:

$15,000.00
Original Start Date: 8/1/2001

Revised Start Date:

Original End Date: 2/1/2002

Revised End Date:

7/15/2003
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Stormwater Management Fund/Drainage Fund

$15,000.00 ---
       
Total Amount: $15,000.00 $15,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Right of Entry 8/1/2001 9/1/2001 12/1/2001    
2. Survey 9/1/2001 10/1/2001 1/1/2002    
3. Design 1/1/2002 1/31/2002 3/31/2002    
4. Construction 1/1/2002 8/15/2002 2/1/2002 9/30/2002    
5. Plat Preparation and recordation 7/1/2002 11/30/2002 7/15/2003    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue
10/15/2003The project has been completed. This is the final report.

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue