Project Detail
Project Main Menu

Project Overview
Project Name: B&FP- Ferlazzo Pkg-ADA
Project Type: Facility/Building
Project Description: The project includes ADA sidewalks, ADA parking and ADA ramp/railing.Project is scheduled to be completed in July , 2020
Project Manager: Mike I. Gibbs     send an email
Alternate Manager:     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $360,143.00

Revised Budget:

---
Original Start Date: 5/11/2020

Revised Start Date:

Original End Date: 5/15/2020

Revised End Date:

Last Updated On: 6/25/2020 Maps  Pictures  Documents


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue