Project Name: B&FP- WDPS Pkg Lot Reconstruct
Project Type: Facility/Building
Project Description: The project involved installation of underground drainage system to fix current deterioration of the rear parking lot. The project is completed with restriping as the only outstanding work.
Project Manager: Mike I. Gibbs     send an email
Alternate Manager:     
Agency Name: QPR?: Yes
Magisterial District: Brentsville
Original Budget: $413,195.00

Revised Budget:

$253,000.00
Original Start Date: 5/8/2020

Revised Start Date:

Original End Date: 7/15/2020

Revised End Date:

Last Updated On: 9/30/2020 Maps  Pictures  Documents



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Project completed. 5/8/2020 7/15/2020 6/11/2020    
2. Project completed. 5/8/2020 7/15/2020 6/11/2020    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue