Project Detail
Project Main Menu

Project Overview
Project Name: ESD: SWM Facility 232 - Water Quality Retrofit
Project Type: Water Quality Retrofit
Project Description: Convert existing dry detention pond to an enhanced extended detention facility. The resulting increase in pollutant removal efficiency will help the County meet its TMDL reduction requirements.
Project Manager: Benjamin A. Eib     send an email
Alternate Manager: Tony Marquez     
Agency Name: Public Works QPR?: Yes
Magisterial District: Potomac
Original Budget: $166,000.00

Revised Budget:

$227,400.34
Original Start Date: 2/5/2020

Revised Start Date:

Original End Date: 6/30/2021

Revised End Date:

Last Updated On: 8/12/2021 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. DEQ Stormwater Local Assistance Fund (SLAF)

$56,863.00 --- 11/14/2020

2. County Watersheds CIP

$109,137.00 $170,537.34 2/5/2020
       
Total Amount: $166,000.00 $227,400.34



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Plan Approval 2/5/2020 12/16/2020 Chao  
2. Construction 1/25/2021 6/30/2021 Chao  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue