Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Judicial Center Renovations Phase I 23C31001
Project Type: Renovation
Project Description: The Phase 1 renovations to the Judicial Center include: Commonwealth Attorney's office, Courtroom #7, Audio/Visual upgrades to 16 courtrooms, elevator(s) modernization, life safety upgrades and HVAC/Building Management systems replacement.
Project Manager: Karen L. FitzGibbon     send an email
Alternate Manager:     
Agency Name: Facilities and Fleet Management QPR?: Yes
Magisterial District: Brentsville
Original Budget: $10,000,000.00

Revised Budget:

$10,000,000.00
Original Start Date: 7/1/2022

Revised Start Date:

Original End Date: 7/1/2023

Revised End Date:

Last Updated On: 8/19/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Capital Reserve-General-FY23

$10,000,000.00 --- 7/1/2022

2. Bldg & Fac. Cap Prog.FY23 GF

$0.00 --- 7/1/2022
       
Total Amount: $10,000,000.00 $10,000,000.00


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue