Project Detail
Project Main Menu

Project Overview
Project Name: FCM: Public Safety Training Center - Classroom Building 22C71001
Project Type: Design
Project Description: The Public Safety Training Center Expansion (PSTC) Classroom Building will be located at: 13101 Public Safety Dr, Nokesville, VA 20181. The Public Safety Training Center Expansion (PSTC) Classroom Building includes construction of a facility containing classroom space, administrative support space and parking area. The training center supports the recruit training of police and fire and rescue system personnel, and ongoing training for active duty and volunteer personnel. The recommended projects are based on the recent PSTC master plan update.
Project Manager: Christopher D. Phillips     send an email
Alternate Manager: Eric Brunner     
Agency Name: QPR?: Yes
Magisterial District: Brentsville
Original Budget: $3,000,000.00

Revised Budget:

$3,000,000.00
Original Start Date: 8/19/2022

Revised Start Date:

Original End Date: 8/19/2022

Revised End Date:

Last Updated On: 11/18/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bond-PSTC FY21

$3,000,000.00 --- 7/1/2020
       
Total Amount: $3,000,000.00 $3,000,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. RFI package delivered to Procurement 6/24/2022 6/24/2022  
2. Published 9/30/2022 9/30/2022 Procurement  
3. A/E Proposals Due 11/10/2022 11/10/2022 Project Team  
4. Pre-Proposal Meeting 10/11/2022 10/11/2022 Project Team  
5. Amendment 1 - Published 10/14/2022 10/14/2022 Procurement  
6. Amendment 2 - Published 10/20/2022 10/20/2022  
7. Amendment 3 - Published 10/24/2022 10/24/2022 Procurement  
8. A/E Proposal Distribution Meeting 11/10/2022 11/10/2022 Procurement  
9. A/E Selection Committee Meeting -1 11/16/2022 11/16/2022 Project Team  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue