Project Name: FCM: Homeless Navigation Center East 22C4402
Project Type: Design
Project Description: The Homeless Navigation Center East will be new building constructed at 14716 Potomac Mills Rd, replacing the existing shelter. The HNCE will provide overnight, temporary, emergency sheltering, a drop-in center and wrap-around services for up to 50 adults experiencing homelessness.
Project Manager: Christopher D. Phillips     send an email
Alternate Manager: Eric Brunner     
Agency Name: FCM QPR?: Yes
Magisterial District: Neabsco
Original Budget: $2,000,000.00

Revised Budget:

$2,000,000.00
Original Start Date: 8/19/2022

Revised Start Date:

Original End Date: 8/19/2022

Revised End Date:

Last Updated On: 8/30/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bond - Homeless Nav. Center East

$2,000,000.00 --- 7/1/2022
       
Total Amount: $2,000,000.00 $2,000,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. FCM delivered electronic RFI package to Procurement 1/27/2022 5/2/2022 FCM  
2. Procurement published RFI package 5/9/2022 5/9/2022 Procurement  
3. RFI proposal response due from A/E firms 6/7/2022 6/7/2022 Procurement  
4. Pre-proposal meeting 5/18/2022 5/18/2022 Project Team  
5. A/E Selection Committee Meeting -1 7/11/2022 7/11/2022 Project Team  
6. A/E Selection Committee Meeting -2 7/29/2022 7/29/2022 Project Team  
7. A/E Selection Interviews 8/17/2022 8/17/2022 Project Team  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue