Project Name: FCM: Station 27 F&R 22C65001
Project Type: Design
Project Description: Station 27 is a brand-new Fire & Rescue station planned for construction at 15825 Spriggs Rd., to house a pumper and an ALS ambulance. Twenty-four-hour career staffing will be provided for both units. The building will include sleeping quarters, a kitchen and dayroom, a physical fitness room, a training room, and offices. The station is currently planned to include two to three apparatus bays and an area for personal protective equipment.
Project Manager: Christopher D. Phillips     send an email
Alternate Manager: Eric Brunner     
Agency Name: FCM QPR?: Yes
Magisterial District: Potomac
Original Budget: $1,400,000.00

Revised Budget:

$1,400,000.00
Original Start Date: 8/19/2022

Revised Start Date:

Original End Date: 8/19/2022

Revised End Date:

Last Updated On: 11/18/2022 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. Bond - F&R Station 27

$1,400,000.00 --- 7/1/2021
       
Total Amount: $1,400,000.00 $1,400,000.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. RFI package sent to Procurement 6/2/2022 6/2/2022  
2. A/E firms proposals due 8/9/2022 8/9/2022  
3. RFI Published 7/19/2022 7/19/2022  
4. Pre-proposal Meeting 7/28/2022 7/28/2022  
5. A/E Selection Committee Meeting -2 8/24/2022 8/24/2022  
6. A/E Selection Committee Meeting -1 8/12/2022 8/12/2022  
7. A/E Selection Cost Proposal Review 9/15/2022 9/15/2022 Project Team  
8. A/E Negotiations 9/30/2022 9/30/2022 Project Team  
9. A/E Finalized Cost Proposal Submittal 10/19/2022 10/19/2022 A/E Firm  
10. A/E Finalize Negotiations 10/19/2022 10/19/2022 Project Team  
11. A/E Contract Item to be presented to BOCS on November 22nd 11/22/2022 11/22/2022 FCM  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue