Project Detail
Project Main Menu

Project Overview
Project Name: PM: Fleet Management Facility
Project Type: Construction
Project Description: Construct new Fleet Management Facility ( 19000 SF). Various divisions within Public Works will be responsible for preparing site plans, grading, clearing, preparing building pad, moving utilities, etc. prior to start of construction. New Facility will house a parts area, lounge, library and office space. Facility will have the ability to service 24 vehicles. Project includes construction of 400SF Tire/Oil Storage building
Project Manager: Said G. Said     send an email
Alternate Manager: Martha A. Clark     
Agency Name: PW Property Management QPR?: Yes
Magisterial District: Coles
Original Budget: $1,200,000.00

Revised Budget:

$1,805,090.00
Original Start Date: 1/28/2002

Revised Start Date:

Original End Date: 11/22/2002

Revised End Date:

8/4/2003
Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. McCoart Space Renovations

$0.00 $58,220.00 6/3/2003

2. Revenue from sale of Land

$0.00 $169,875.00 8/12/2002

3. Transfer fro Enterprise fund ($59485)and Fleet ($10)

$0.00 $59,495.00 8/12/2002

4. Carryovers from FY02 Budget

$0.00 $317,500.00 8/6/2002

5. General fund

$1,200,000.00 $1,200,000.00 7/1/2001
       
Total Amount: $1,200,000.00 $1,805,090.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
Assigned
Staff
 
1. Obtain right of entry 2/14/2002 3/6/2002 Transportation.  
2. A&E Design 2/14/2002 3/29/2002 Moseley  
3. Survey 2/18/2002 3/11/2002 Burg.& Niple  
4. Clearing 3/4/2002 3/21/2002 Env. Serv..  
5. Site Design 1/28/2002 3/15/2002 Watershed  
6. Final Site Plan, revised per VDOT, Water line 3/18/2002 4/5/2002 8/8/2002 Watershed  
7. Site Permitting 4/8/2002 4/22/2002 Prop.Mgmt.  
8. Construction Plan Review 1st. Submission 4/15/2002 4/19/2002 5/10/2002 5/30/2002 Bldg. Dev.  
9. Revise Plans 5/13/2002 6/1/2002 5/27/2002 6/23/2002 Moseley  
10. Construction Plans 2nd. Review 5/28/2002 6/25/2002 6/10/2002 7/19/2002 Bldg. Dev.  
11. Site Preparation, Clearing, Rough Grading 4/8/2002 5/3/2002 Env. Serv..  
12. Utilities Design 3/25/2002 4/8/2002 Watershed  
13. Construction of New Waterline 4/8/2002 9/23/2002 5/3/2002 5/8/2003 Solid Waste  
14. Ad & Bidding 4/24/2002 7/22/2002 5/21/2002 8/12/2002 Purchasing  
15. Contract Award 6/4/2002 9/3/2002 6/4/2002 9/3/2002 BOCS  
16. Structural Shop Drwg. submittals 6/4/2002 9/16/2002 6/11/2002 9/25/2002 Contractor  
17. Review of Shop drawings 6/18/2002 9/26/2002 7/1/2002 10/10/2002 Moseley &BD  
18. Preparation of building Pad 5/27/2002 10/16/2002 7/5/2002 11/22/2002 Env. Serv..  
19. Construction of Bldg.foundation and slab 7/8/2002 11/22/2002 7/26/2002 1/8/2003 Contractor  
20. Manu. of Steel Structure 7/2/2002 10/16/2002 7/26/2002 12/9/2002 Inland Bldg.  
21. Construction of building structure 9/5/2002 1/2/2003 10/3/2002 3/28/2003 Contractor  
22. Interior Construction 10/3/2002 1/21/2003 11/21/2002 4/25/2003 Contractor  
23. Project Closeout 11/22/2002 4/25/2003 11/22/2002 7/11/2003 Contractor  


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue