Project Name: PM: Owens OIT Computer Operations and Data Center
Project Type:
Project Description: Reconfiguration, consolidation of equipment, servers and computers located in the Computer Operations Center on the lower level of the Owens Building. Work includes procurement and installation of equipment rack enclosures, command stations and work stations, moving and grouping of equipment and servers in racks. Data, fiber optic and network cabling and additional runs for electrical wiring are also required.
Project Manager: Said G. Said     send an email
Alternate Manager: Martha A. Clark     
Agency Name: Property Management QPR?: Yes
Magisterial District: Coles
Original Budget: $223,437.00

Revised Budget:

$223,437.00
Original Start Date: 12/1/2000

Revised Start Date:

Original End Date: 2/28/2002

Revised End Date:

Last Updated On: 5/2/2004 Maps  Pictures  Documents


Funding Source    

Description

Original
Budget Amount
Revised
Budget Amount
Funding Date

1. FYOO Carryovers

$223,437.00 ---
       
Total Amount: $223,437.00 $223,437.00



Tasks/Milestones     Show GANTT Chart
Task/MileStone Start Date
Original Revised
End Date
Original Revised
   
1. Design by County Staff 12/1/2000 3/1/2001    
2. Prepare Technical Specifications for racks and stations 3/14/2001 3/30/2001    
3. Bidding for racks and stations 4/1/2001 5/1/2001    
4. Contract award 6/11/2001 6/11/2001    
5. Procurement of Materials and Installation 7/15/2001 1/31/2002    
6. Completion of Project-- Fully Operational 2/28/2002 2/28/2002    


Comments/Issues     Show All Issues

1. Service/Policy Issues   

 

Date

Issue

2. Schedule/Timing Issues     

 

Date

Issue

3. Fiscal/Resource Issues     

 

Date

Issue

4. Impact on Other Projects     

 

Date

Issue